News Brief
New
Gloucester--Work on the Bald Hill Road Bridge continues.
So far the work that has been completed includes all
utilities have been transferred onto new poles and
are out of the way. Clearing has been completed, and
signing and temporary erosion control measures are
finished. The temporary bridge and detour is completed
and traffic switched over onto one lane traffic with
lights. Two cofferdams are installed and existing
abutments are removed.
Upcoming schedule of work includes placing a seal
on the abutment within 2 weeks, placing footing on
two abutments within 4 weeks, and placing precast
for May 5.
The Department of Transportation inspects bridges
and rates their viability- the Bald Hill Road bridge
had been placed on the critical list. It is being
repaired, almost nearly reconstructed. The work is
scheduled for completion by June. Craig Hurd is the
MDOT Resident Engineer for the project and the project
identification number is 10157.56.